You signed the lease. The new suite is ready in eight weeks. You call your IT company on week six to let them know.
That call comes too late for everything that matters. Business-class internet at a new address requires a circuit order that takes 30 to 90 days to provision, sometimes longer depending on what infrastructure exists in the building. Phone number porting is governed by FCC rules (47 CFR §52.35) that give carriers up to four business days for complex ports, and any error in the paperwork restarts the clock. Structured cabling, if the suite needs it, has to be scheduled, permitted, and run before furniture arrives.
This checklist organizes the work by how far out you need to start. If your move is less than 90 days away, read this and then figure out which items are already behind.
90 Days Out: The Long-Lead Items
Order your business internet circuit
Internet at a new commercial location is not a same-week setup. According to MHD IT, new business circuits typically take 30 to 90 days to provision, and that window extends further when the building requires a new fiber run to the suite or a carrier has to pull cable to the MPOE (minimum point of entry) for the first time. Start the conversation with your provider the same week you sign the lease, not the same week you move furniture.
If the building does not have fiber and you want it, the carrier may treat this as a new build. That can push lead time to three to six months and carry installation costs of $10,000 to $50,000 depending on distance (source: JumpStart Technology, 2026). Knowing this before you commit to a move date matters.
Confirm carrier availability before you assume
Not every carrier serves every building. Before you order, ask your provider whether they have existing infrastructure at the address and which floor. If the building is not on their network, you are either waiting for a new build or switching carriers. Run this check the day you sign, not the week before you move.
Assess the building’s existing cabling
Commercial buildings vary widely. A suite that was previously occupied by a tech company may have Cat6A cabling in good condition. A suite built out before 2018 may have Cat5e or older, which limits you to gigabit speeds and does not support Power over Ethernet for cameras and access control at modern distances. Buildings with no tenant improvement work done will often have bare conduit or nothing at all.
Walk the space with someone who can look at the existing drops, check the patch panel in the server closet (if one exists), and tell you what you actually have. Retrofitting cabling after furniture is in place costs three to five times more than running it during the buildout.
60 Days Out: Planning and Procurement
Get your cabling scope and quote locked
Once you know the layout of the new space, finalize the number of data drops, where cameras and access control readers will go, and where the server rack or IDF will be located. A structured cabling contractor needs this information to quote accurately. Cat6A installation for a commercial office retrofit typically runs $150 to $300 per drop, according to Camali Corp (2025). A 5,000-square-foot Cat6A installation can run $8,000 to $15,000 depending on complexity.
Getting a quote does not mean you have to start work in week one. It means you have a number, a scope, and a contractor who is reserved for your date.
Order hardware with lead times in mind
Switches, servers, and enterprise networking equipment are not available on-demand. As of 2026, Reliable Technology reports that hardware lead times for switches and servers run eight to twelve weeks. If your move requires a new server, a new core switch, or additional wireless access points, order them now. Waiting until month two to place hardware orders creates a scenario where your move date arrives before the equipment does.
Confirm the phone porting timeline
If you are moving your existing business phone numbers to a new service or a new provider at the new address, file the port authorization request early. Under FCC 47 CFR §52.35, carriers must complete simple ports within one business day and non-simple ports within four business days once they have a valid, complete port order. The word “once” is important: incomplete submissions get rejected, and the clock restarts on the corrected order. Confirm with your phone provider what documentation they require, submit it completely the first time, and add a week of buffer for any back-and-forth.
One thing to verify before you sign: Ask the building manager which carriers have existing infrastructure at the address. If your current provider is not in the building, you will need to either bring them in (slow and potentially expensive) or switch providers (fast but requires porting your numbers). Finding this out before you sign the lease gives you something to negotiate with.
30 Days Out: Active Work Begins
Start the cabling installation
Cabling work happens before furniture. Confirm with your contractor that they are scheduled for a specific date and that you have the keys or site access arranged. Most commercial leases give you possession a few days before your official move-in; use that window for cabling. Running cable around desks, under rugs, and through existing furniture costs more and takes longer.
Confirm circuit status and escalate if needed
Check in with your internet provider and ask for a provisioning update. If the circuit was ordered 60 days ago, you should have a firm date or at least an estimated completion window. If you do not, escalate now. Carriers have project managers who can pull circuit orders forward when customers make noise at the right time. Waiting passively until move day to find out the circuit is not ready is the most common avoidable IT failure in a business relocation.
Plan the server and phone system cutover
If you are moving physical servers, coordinate with your IT provider for the physical move and reconnection. Allow for a day of configuration work before expecting full function at the new site. VoIP phone systems that are hosted in the cloud require only an internet connection and configuration; on-premise phone systems require the physical equipment to move and come back up correctly at the new address.
Move Week: Cutover and Verification
Test internet before furniture arrives
If you have keys before the official move date, get someone in the new suite to confirm that the circuit is live, the router is configured, and basic connectivity is working. This gives you time to call the carrier if something is wrong before two hundred people are trying to work there.
Bring security cameras and access control back online
Camera and access control systems are the most commonly forgotten IT items in a move. They need network connectivity, mounting hardware installed, and configuration. If your existing system uses an on-premise NVR or DVR, it needs to be physically moved and reconnected. If you are running cloud-managed cameras, they need to be remounted and connected to the new network. Access control credential databases need to be confirmed at the new hardware.
Confirm phone number portability is complete
Do not assume the port completed. Test each number by calling it. Confirm voicemail is routing correctly. Confirm any auto-attendant or ring group is working as expected. If you have customers who call you, this is not a detail to skip over on move day.
The Cost of Getting This Wrong
The most expensive office move IT failure is not a lost cable or a misconfigured switch. It is a business that cannot take calls and cannot access its systems because a circuit order never got filed, or got filed too late to deliver on time.
Consider a business doing $6 million per year. That is roughly $500,000 per month, $25,000 per working day. Five days of IT-driven downtime during a move represents $125,000 in lost revenue opportunity, plus staff time spent working around the problem. The circuit provisioning that takes 30 to 90 days costs a few hundred dollars per month to run. Filing the order eight weeks late can cost twenty times that in a single week.
If your move is coming up, the most useful thing you can do today is call your internet provider, ask whether they have existing infrastructure at your new address, and find out the current circuit provisioning lead time for that location. That one call tells you whether you are behind or on track.
Working with an IT provider on your move? The right partner handles circuit coordination, cabling oversight, hardware procurement, and cutover planning as part of the engagement, not as add-on billing items you discover later. If you are planning a relocation in the Atlanta metro area, we handle this end to end. See our office relocation services page for how we approach it.